Minutes of the Buildings & Site Development Committee Meeting 8th May

2013-05-28T12:29:17+01:00

Present :  Stephen Grosvenor, Mike Palmer, Daniel Pitt, Mark Antell, Reg Hardwick

Aplogies:Kevin Penfold, John Plaister

Item 1. MP said a short prayer.

Item 2. Minutes of last meeting – reviewed – apologies due to Reg who, despite providing valuable input to the March meeting, got missed off the present list due to the chair’s poor counting skills.

All outstanding items have been included in the agenda.

Item 3. –Budget Summary  – see cumulative spend at the end of these minutes

Item 4. – Christ Church

a) West porch Project. Following the communication exercise to demonstrate the church plans for the porch there have been no particular objections or indeed feedback of either flavour. SG proposes that we proceed to getting a more detailed proposal from Antony our architect – this will form the basis of a submission for faculty permission from the diocese and will provide more detailed information on the advantages and benefits of the proposal. AFK has provided a quote of £1,600 ex vat to supply the necessary designs – his estimate of the cost for the porch is in the region £10-£15k – this will include the remodelling of the rear space to improve flow and a new position for the audio/visual control board.We will aim to complete this work prior to this winter. ACTION:SG to accept fee proposal from Antony Feltham King.

b) LED Lighting –  We have had some positive reactions to the lighting proposal. We have now been given a temporary licence to proceed with the trial in the Lady Chapel – this will allow us to see how the LED lights perform over time – under the licence we have until August 2014 if necessary ACTION: MP to contact Binary electronics and get final current cost proposal for the trial and give the go ahead.

 c) AV update – Considerable progress has been made due to the hard work of Bernard, supported by Mike to install a set of new compliant (and working) wireless microphones. We now have 4 new wireless mikes and 1 new Handheld. These are fully compliant with latest legislation and have much better controls and displays which allow their battery and other information to be more easily monitored. The Church has saved a substantial sum for installation costs due to Bernard and Mike’s intervention so many thanks to them both for their care and professionalism.

 MP has also made contact with a local sound recordist who has offered to help us trial some different recording microphones for the choir and organ. This should help us get a better idea of what to buy and where to position any new static microphones.

 d). Damaged South transept window. Dan Pitt has offered to take this forward as it has not been receiving the attention it requires recently. The Friends have already offered to help to offset some of the costs for this project which is gratefully accepted. Dan will seek some quotes and work with John Plaister who has some experience  in this area. ACTION – DP to get quotes for repair

 f) Asbestos removal from old boiler room. We have already had an estimate and this work should now be done as soon as possible.  ACTION MP to find quote and confirm costs – proposal is to proceed to get the works completed so we can continue to safely use the storage.

 

Item 5. St Mary’s Church – the paintwork in St Mary’s is in a poor state of repair. We will add it to the work in progress list and review options for getting it done.  ACTION MP to see if Community Service Volunteers would do it.

 

Item 6 Community Centre update

a)   Ground source heat pump bore holes have caused a small delay of a week due to geological factors. Foundation work is due to start in the next few days.

 b)   Works timetable – Despite the small delays we are still on target for September completion. There are a number of things to do involving groundworks and foundations as well as the relocation of the Morris memorial. This will happen in the next 3-4 weeks. The building should arrive in June.

c)    Rubbish arrangements –The burning pile has been cleared ready for the new Garden. We have entered into a joint contract with the burial board for a Biffa waste disposal service. The new regime for rubbish and recycling in the burial ground and church is now underway. The winner of the garden design competition has been announced and MP and SG will discuss with Ian Handy our advisor and the winner to work out how the design can be realised.

 d)   Kitchen Design – We are in consultation with external caterers and equipment suppliers to confirm the specification of the kitchen equipment. The intention is that it should be commercial quality, capable of supporting significant catering events in the new hall.

 e)   Archaeology – As part of our planning permissions we are required to hire an archaeologist to complete a watching brief as we start foundation digging – this contract has been subsumed into the Timberworks project to save VAT costs.

f)    Cost Updates – It is important to keep a close eye on the costs to ensure that we can get the best possible results for our limited budget. Where relevant we have added some items into the contract cost to reduce our liability to pay VAT.

 Current Contract cost –                                                         £629,861

                   Repair of existing paths & lighting  (est.)                    £6,000

Garden of reflection         (est.)                                      £4,000

                   Community Artwork                                                         £4,000

                   Addition of commercial kitchen facilities                    £8,000

Total costs                                                                                £652,831                                               

 Funding sources

        Devizes Road hall sale funds                                   £247,000

       D&R funds                                                              £23,000

              SBC grant                                                               £230,000

              LCF grant                                                               £46,000

              Garfield Weston grant                                             £5,000

              Sale of Parish office   (est)                                        £105,000

Total funding                                                              £656,500

The above illustration assumes that we “loan” £105k from the general funds until such time as the parish office can be sold. It also shows that the funds allowed for contingencies are almost exhausted. We are continuing to make grant applications towards securing Kitchen equipment, new chairs and tables for the hall and are considering local targeted appeals to businesses and individuals for specific items such as the artwork, garden costs and kitchen facilities

Item 7 Property Checks –

As a  result of Annual Property check carried out on 32. Points a & b & c are outstanding

a)   Re-plastering required following difficulties with damp and mould in the dining room. ACTION MP to recommend some plasterers to occupant so that she can arrange for them to visit and quote.

b)   PV Front door may need replacing as it doesn’t fit properly and is very drafty – SG suggested it might be fixable – details of the Double Glazing doctor to be passed on to Karen at the same time as MP recommends plasterers – Double Glazing doctor   01793 431788.

c)    The light fitting over the stairs is broken and cannot safely be replaced due to its position.Also radiator leaking ACTION: MP to get quote from Gary Hall for both jobs.

 

Item 8 Any other business

Next Meeting: 17th July 7.30 – 51a Broome Manor Lane, SN3 1NB

 Deferred Jobs list

Job

Quote

Date

Rated A/B/C/D

SW door repair and draft exclusion Defer to D&R 20/01/2010

C

Pressure washing the vestry steps    

C

Flooding under the clergy vestry   25/03/2010

C

Cycle Racks Defer to new hall 27/07/2010

C

Wall mounted Notice board at West door £95+VAT 31/03/2011

C/D

Free standing Noticeboard at West door £375+VAT S&I 31/03/2011

C/D

Sign for Church Centre (maybe directional signage   rather than the name) Defer 31/03/2011

D

New fireproof ceiling in the undercroft Defer 20/02/2012

B/C

New central heating boiler & rads  31 CS Complete 17/10/2011

C

Asbestos removal – church awaiting 14/11/12

B

New boiler for 32 Cricklade Awaiting   quotes 14/03/2013

B

South transept S &West window repairs Seeking quotes 14/11/12

C

Remove nave screens from the front pews to aid flow  from families and young people during services.

Defer- issues identified with H&S and costs. 19/01/2013

D

Repainting St Marys Reviewing options 09/05/13

D

New smoke alarms 32 ? Carbon monoxide monitor? Reviewing options 09/05/13

C

 

A- Assessed as high risk

B- Legal requirement

C- Best Practice.

D – Nice to do.

Cost Schedule 2013 Year to date

Job Date Contractor Sum paid
L.C. Toilet repair Jan D.Hobbs £60.00
Damp fix – 31 Feb In house £54.00
Boiler Checks Feb D Hobbs £156.00
Boiler replacement -32 May G Hall £3,000
Tree Pollarding May N Freshwater £650
       
       
       
       

 

Minutes of the Buildings & Site Development Committee Meeting 8th May2013-05-28T12:29:17+01:00

Community Centre Progress

2013-04-12T23:47:22+01:00
20130320_161453

Work underway on the new Western entrance

The building process is now fully underway. You can find out more details about the building and its features on an information board at the rear of the church. We also have an Photo gallery showing the progress of the build. For the period of the build Timberworks, our contractors will do everything they can to minimise disruption caused by the works. Unfortunately however, demolition, drilling and general ground works will inevitably be noisy and sometimes disruptive as vehicles come and go around the site.Please also be aware that site works can be hazardous so please obey all signs, warnings and instructions given by the Contractor’s staff – they are responsible for ensuring the safety of the site. If you have any queries please contact Tom Marriott our Project Manager, on his mobile; 079006 720 45

View the picture gallery.

 Timetable of Works

  • Contract Signed – February
  •  March 18th – Timberworks, our contractor, take over the site
  • Work starts to move gravestones and prepare Western access for build and demolition.
  • April 1st   – Demolition of the old centre and site clearing begins.
  • April 15th – Boreholes for Ground source heating.
  • May 1st     –  Ground works – creating foundations for the new building.
  • May 21st   –  Building commences
  • End  August – Building work complete.
  • September  1st – Open for business
Community Centre Progress2013-04-12T23:47:22+01:00

Buildings and Site Development Committee – March 13

2013-03-19T10:22:39+00:00

Present :  Stephen Grosvenor, Mike Palmer, Daniel Pitt, John Plaister

Aplogies: Mark Antell,Kevin Penfold

SG said a short prayer.

 Item 2. Minutes of last meeting – reviewed – agreed.

All outstanding items have been included in the agenda.

Item 3 –Budget Summary ytd £596.00

Damp solution – redecoration 31 Cricklade £54

Boiler Checks – £156

Action SG to add 2013 costs to each minute to build up a complete history of costs per year.

Item 4 – Christ Church

 a) West porch plan. We have now received an outline proposal from AFK which broadly establishes that the restoration of the west porch is feasible. He has supplied some sketches which we will use as part of a broader consultation exercise with the congregation. ACTION:SG to discuss possible costs with AFK.

b) We will need DAC faculty for the porch – the plans incorporate removing a small number of pews at the rear of the church to increase the circulation space and to accommodate a new position for the Audio visual console.

c) LED Lighting AFK and Binary electronics have had a fruitful collaboration and have created a new design proposal for an LED based pendant lighting scheme. We will use this to communicate the proposed LED trial in the Lady Chapel to the wider congregation and initiate a discussion on lighting in general. ACTION: MP to complete temporary licence application – SG to write to the DAC and advise them of our intentions re the lighting and seek their support. SG to forward the designs and proposal to PCC (Peter Ford) for a resolution to commit to the LC trial

d) AV update. MP updated us on the latest quote and advice from SMS. They have quoted an overall figure of £12k to cover our basic requirements plus a new mixing console. Their advice was however that we could probably do the installation of new radio mikes and receivers ourselves. Bernard Oxborrow has been thinking about how this could be done. Proposal to replace 2 of the broken radio mikes with new ones accepted– this will solve our immediate problems. We can then review performance and decide on the next steps.

e) South transept window repairs – No further progress on this at this time. ACTION SG to follow up with AFK for his suggestions on masons and with Rob Fleming who is going to be doing some of our monument moving.

f) Asbestos removal from church undercroft. We have had a quote and this work should be done as soon as possible. ACTION MP to find quote and confirm costs – proposal is to proceed to get the works completed so we can continue to safely use the storeage.

Item 5. St Mary’s Church – no current issues

Item 6 Community Centre update

a)   Works timetable –  as part of the general communications on D&R planned for next Sunday, SG has produced a comms board explaining the order of work, timetable, information on the design, GS heating & Solar panels etc.

b)   Kitchen Design – We are unable to claim kitchen equipment (Cookers, Fridges etc as zero rated under the main project so we have elected to source the equipment and design ourselves. The intention is to have a well-equipped, good quality, finishing kitchen capable of delivering community style catering requirements. Designs are being developed and consultation with interested parties will start in the next couple of weeks.

c)    Contractor. Timberworks has been selected as main contractor for the works and the contract was signed in February as planned. The contract value is £612k but the outstanding quotation from Southern Electric to provide 3 phase electric power to the new centre has now come in at £12,745 making a total estimated spend of £624k.

d)   Burial Ground lighting proposal. As part of the contractors quote we have included an external lighting ring. We intend to install suitable low level lighting to the pathways around the churchyard to ensure safe access. Details of the installation will be finalised later in the year.

e)   Hall contents and reclamations. In line with our previous proposals to sell off or donate the unwanted hall contents MP reported a contribution of £172 to D&R funds from the sale of assorted tables, screens and redundant electrical equipment – thanks go to Mike and ebay. The wooden floor has been comprehensively reclaimed and donations have been received from the new proud owners of a bit of CC history – this has earned around £800 so far.

f)     Rubbish arrangements – Once we have cleared the existing burning pile ready for the new Garden, it will be important to establish a new regime for rubbish and recycling in the burial ground and church. We have made provision for a new hard standing area for rubbish bins at the N.E .end of the car park but we need to finalise the refuse policies and supplier as soon as possible. This is being done in partnership with the Burial Board. ACTION MP to follow up with Bernard and Pam.

g)    Access – there may be some difficulties with access to the church during busy periods on site – the Alms house residents may be affected as the drilling for the GS heating is done. MP has spoken to Harry – Timberworks will be circulating contact details of the site foreman so that everyone knows who to talk to if there are any issues.

Item 7 Property Checks –

Annual Property check carried out on 32.

a)   Re-plastering required following difficulties with
damp and mould in the dining room. ACTION MP to recommend some plasterers to occupant so that she can arrange for them to visit and quote.

b)   PV Front door may need replacing as it doesn’t fit properly and is very drafty – SG suggested it might be fixable – ACTION – SG to hand details of Double glazing doctor to occupant to see it he can fix it. If not we will need a quote for a new door.

c)    The light fitting over the stairs is broken and cannot safely be replaced due to its position. ACTION: Find electrician willing to move the fitting to a more accessible position

d)   The boiler has failed and has a leak – it is recommended to replace – we have a proposed plumber – Gary Hall. ACTION: Get quotes

e)   Thanks are owed to Daniel P who has sorted out the reported damp in 31 The room has been de-moulded and the wall paper stripped and repainted.

f)     New smoke alarms fitted in 31 but are needed in 32.We also need to fit Carbon Monoxide monitors.

Item 8 Any other business

  1. Weshould review the PAT testing process/ fire extinguisher checks

Next Meeting: 8th May 7.30 – 51a Broome Manor Lane, SN3 1NB

Buildings and Site Development Committee – March 132013-03-19T10:22:39+00:00

Church Centre Closes

2013-03-26T14:36:31+00:00

Following over 40 years of valuable service to the community, the Old Church centre has finally closed its doors for the last time. Contracts have been signed for the new building which should be ready at the end of the Summer. Our contractor Timberworks Europe will officially take responsibility for the site as from 18th February and will start a programme of groundworks, road widening and other preparatory activities during the next couple of weeks.

CC demolition_ 170213

The old hall minus its hard wearing wooden floor.

Last week saw various groups removing salvageable items from the centre including the fine wooden floor and various other fixtures and fittings. Previously, unwanted items had been offered and sold on Ebay and donated via Free-cycle.  The remaining items have been placed in storage.

The build process will inevitably cause some disruption – we have had to install temporary toilets at the South West door of the church and on some days during the groundworks and build programmes, it will be necessary to control access to areas of the paths around the church for health and safety reasons. As soon as we have a full programme of works we will publish it and ensure that everyone knows what is going on.

In the meantime if you would like to know more about the new community centre or become involved in its planning, operation or management then please contact the project team –  Stephen Grosvenor (s.grosvenor@gmail.com 07885 217077) or Mike Palmer (michaelailsa@o2.co.uk 07835 582414).

 

 

 

Church Centre Closes2013-03-26T14:36:31+00:00

Minutes of the Buildings and Site Development Committee

2013-02-04T11:43:22+00:00
Billiard3

Keith a National Trust conservator gets the table ready for its trip to Cumbria and its new home in Wray Castle

The committee met for the first time this year. You can read the full minutes of the meeting here. We are now only weeks away from the start of the Community Centre build project.

If you would like to comment or offer practical help to the Community Centre project then please contact Stephen Grosvenor (s.grosvenor@gmail.com) or Mike Palmer (michaelailsa@o2.co.uk)

Minutes of the Buildings and Site Development Committee2013-02-04T11:43:22+00:00

Upper Seagry Community Hall

2013-03-01T12:19:56+00:00

As part of our research and selection process we have visited a number of existing centres including this one in Upper Seagry near Chippenham. We have learnt a lot from these visits and are grateful to the, often, volunteer helpers and project managers who have delivered these excellent community resources. Our new centre will start to be built in Spring 2013.

Upper Seagry Community Hall2013-03-01T12:19:56+00:00

Questions and answers about our Church site development Plans

2012-11-29T16:13:38+00:00

 Q. Why are we doing all this? Can’t things just stay as they are?

A. Our vision is that Christ Church, its community centre and the grounds welcome growing numbers of people throughout the week. The renewal work that we undertake will be guided by an overall strategy of creating sustainable, energy efficient, environmentally responsible buildings that will be more cost effective to run. In the church, we will preserve and restore the original features of the building and enhance its capabilities to deliver excellent sound, lighting and visual experiences to both church goers and other visitors. It will provide a warm and adaptable space for worship, exhibitions, meetings and concerts but always retain its original role and character as a place of peace and reflection. We believe that we have a responsibility to preserve it; not simply as a monument, but as a working, vibrant, educational and useful place – at the centre of the community.

At the same time, we are replacing and extending our current leisure centre to provide more flexible, cost effective and improved facilities to the local community. Our new community centre will put excellent meeting, leisure and refreshment amenities into the heart of Old Town. Like the thousands of people who raised the £8,500 it took to build the original Christ church 160 years ago, we would love you to support us to attain this vision of growth and development – so that we, like them, can keep Christ Church and its work, at the heart of Swindon.

 In the Church

 

Q. Are the pews going to go?

A. As part of the interior works to the church itself, we intend to level the floor and install under-floor heating supplemented by new, energy efficient conventional wall mounted radiators. This means that we will need to replace our existing, platform mounted pews with new free-standing pews in the centre of the church. The remaining pews in the side aisles will be replaced by our existing chairs. We are currently looking to retain the existing historic pews and will search for ways to make them more comfortable and secure.

Q. What are the plans for the Lady chapel?

A. We intend to leave the Lady Chapel as it is.

Q. Our existing lighting is not very energy efficient or particularly effective – are we planning to do something about them?

A. We are looking into new lighting schemes for the church and are interested in LED lights as a very energy efficient and cost effective solution. We will be seeking quotations during 2013 for lighting solutions that will enhance the ambience of the church, cost less to run and maintain and provide more effective lighting.

Q.What surface will the new flat floor have?

 A. We anticipate creating a stone or tiled hard floor. This will improve the thermal efficiency of the under floor heating as well as the acoustics in the church.

Q. One of the reasons the church is so cold in winter is that there are drafts from the doors at the South & West end. What are you doing to improve that problem?

A. We originally investigated a large glass screen at the rear of the church but have now discounted this for cost reasons. Our current plan is to reinstate the interior porches to provide a draft screen for both South & West doors. We will be seeking designs and quotations for this work in early 2103.

Q. Will the Chancel and choir stalls remain as they are?

A. We have no plans to change the choir stalls or chancel area.

Q. This project has been going on for a long time. When will it be all done?

A. We have consulted and researched carefully as this is a once in a lifetime opportunity. Our current timeline is for the new community hall to be completed in mid 2013 and provided that our fund raising and grant applications progress well, we would hope to start work on the church interior during 2014.

 

Q. Why aren’t we repairing the roof first?

A. We have received estimates of over half a million pounds to renovate the whole roof and have so far, been unsuccessful in getting grant assistance on the grounds that it is not bad enough. We felt that hard earned funds would be better deployed in the short term to deliver a warmer, more comfortable, efficient and better equipped church. In the meantime we are making annual accruals for on-going roof repair and patching in our buildings budget to ensure that the building remains dry.

Q. Who makes all these decisions?

A. The P.C.C. authorised a group of church members to create a Buildings and Site Development Group. This group has continued to develop the excellent work of the Development and Renewal group and has consulted widely and conducted a full review of our current situation and made recommendations as to how we can create and develop a sustainable presence in Swindon for the next 160 years. These plans have been presented to the PCC for agreement and approval. They also manage the day to day maintenance and management of all the parish’s properties.

Q. How is the fund raising organised?

A. It is important that we keep clear records on giving to comply with legislation and to maximise our income from gift aid. To ensure that all gifts made to Christ Church are properly accounted for, we make it clear in all Development & renewal fund raising activities that sums raised will go to the D&R fund which is administered separately from our day to day giving. If you wish to give to the D&R fund then please make it clear when you make your gift that it for this purpose, if you do not then we will assume that your gift is for the everyday running of the church and its mission unless otherwise stated. We also actively seek grant funding from relevent trusts and foundations. We always need help in this task. If you have some spare time and would like to help us then please contact the parish office – parishoffice@christchurchswindon.co.uk

 In the Community Hall

Q. Will people come to a community centre if it is connected with a church?

A. We will simply continue the tradition and practices of the past 50 years during which time we have successfully offered our local community full access to our Leisure centre. We already welcome a wide range of local groups and organisations and the plans to extend and develop the facilities that we can offer will mean that we can cater for a wider range of activities as well as providing a more flexible, attractive and contemporary space right in the heart of Old Town.

We intend to create a modern, cost effective community hall in place of our old Leisure centre which will be owned and managed by the church community for the benefit of all. We consider this to be part of our duty as Christians to provide hospitality and a welcome to all regardless of race or creed.

 Q. How much will the hall cost?

A. The current plans are estimated at around £650,000. A large proportion of this will be met from the funds from the sale of the old church hall in Devizes Road. We also intend to integrate the parish office into the new hall which will enable us to sell the existing building. We have secured a contribution of £230,000 from the Borough Council as well as community grants of £50,778 from the Landfill Communities Trust and £5,000 from Garfield Weston Foundation. We now are in a position to start building in early 2013.

Q. Won’t the council want to control how we run the hall?

A. The council will be contributing a substantial sum towards the total required and as such will require us to comply with all planning and  legislative obligations but we would have done this anyway. Ours is the major investment and we will be in full control of the operation and management of the hall. We intend to do this as laid out in our constitution and church plan for the benefit of the wider community.

Q. What will be different in the new hall?

A. We have researched the local hire market and thought about what sort of things we as a Christian community would like to be able to offer our friends in Old Town. Overall we will have a larger building – as a modern structure it will comply with all energy efficiency regulations and, as such, it will be much more cost effective to run than our current hall. In the designs we are exploring, we are looking for greater flexibility in the use of the space available. Broadly we intend to have a large hall to accommodate up to 150 seated, a modern kitchen capable of servicing this number, meeting rooms /office areas and a self-contained public area which we hope will serve those visiting the burial ground or the church itself.

Thousands of people visit the church and burial ground each year and we hope to be able to provide them with a welcome, a friendly face and modern facilities. The flexibility of the new hall will enable us to offer more cost effective rates for smaller groups as well as provide more competitive and modern facilities to larger ones.

Q. What will happen to users when the building work starts

A. We anticipate that, on our current timetable, building work will start in Spring 2013. We have deliberately chosen a modular building style which means that build time will be much quicker than a conventional build. We have been advised that the hall will be out of action for 10-12 weeks. During this time, where appropriate and practical, we will invite users to use the church itself. We will also explore with our fellow partnership churches the use of their facilities. It is important to us that all of our faithful customers are looked after and that they can come back to a new, revitalised and usable hall when work is completed.

Q. Why do we need to spend all this on a new hall when we could use it towards the work in the church itself?

A. We had a surveyors report on the hall last year which identified that it would cost nearly £100,000 to complete the repairs necessary and this would only extend the building’s life by a relatively short period. At the same time, we had an opportunity to bid for the Borough’s Social fund (Section 106 grant). We believe that the solution to the preservation of the church lies in reaching out to our local community to encourage them to find out more about us, discover the value of our (largely hidden) work in the local area and by doing so, come to recognize the contribution that Christ Church makes to Old Town and Swindon.

We believe that a new modern hall at the heart of Old Town will create more opportunity for us to connect with our community by enabling us to better engage with visitors, local charities, organisations and families through the new hall.

Q. Will we be able to afford to run the new hall?

A. The current hall is poorly insulated and expensive to run. Our plan is to build the new hall to the latest insulation and energy efficient standards. It will have solar panels to provide free electricity and a ground source heat pump for heating. It will be designed as a highly sustainable and low maintenance building. Even though the new hall will be larger, we expect it to be cost effective to run and this, coupled with the new flexibility of space, will ensure that we are able to remain within budget in the longer term. We have been given a church commissioners grant towards the cost of employing a Community Development manager to run our halls and to actively market the facilities and seek better links with our local community.

Q. Some of the plans seem to have new paths crossing the current burial grounds – what will happen to the monuments that are currently there?

A. It is important for us to improve access to the new hall. There will be 3 access points; One at each end of the new building and a main entrance opposite our South transept door. The current slope presents difficulties for some, so we are examining ways to access the new building by minimising the slope of the paths. This may involve moving a small number of monuments. We have documented and photographed all the potentially affected stone in the area to the South of the church and have been making efforts to contact the families of those buried here. We have now made an application to the Diocesan Advisory Board to make the changes and this is currently under consideration.

We have more information and plans of the proposed works here. There is no intention to disturb any of the graves in this area – all works will affect only the surface.

If you would like to know more or help us with our church or community renewal plans then please contact the Parish office 01793 522832 or parishoffice@christchurchswindon.co.uk or see our website for more information. www.christhcurchswindon.co.uk

 

Questions and answers about our Church site development Plans2012-11-29T16:13:38+00:00

Site Development News

2012-11-29T16:12:50+00:00

St Mary’s Hall – 5th September 2012 Meeting Minutes

 

Present :  Reg Hardwick, Stephen Grosvenor, Mike Palmer, , John Plaister, Mark Antell, Daniel Pitt.

Apologies: Kevin Penfold

 

SG said a short prayer.

 Item 3. Minutes of last meeting – reviewed and accepted. All outstanding items have been included in the agenda.

 Item 4 –Budget Summary for 2012

We have currently spent c£4,917 Year to date. We have outstanding bills for the Asbestos surveys for the churches & halls and Dave Hobbs bill for heating installation at 31. Our estimated current spend is £10,137 as at end Sept 2012.

 Item 5 – Christ Church

We have put our recommendations for Phase1 Works to the PCC and they have been accepted. These are:

  1. New lighting scheme
  2. Restore the West door internal porch to reduce the draughts
  3. Update the audio/visual facilities in the church.

 We need to make a DAC application for the access works to the hall within the next couple of weeks – PCC must agree to the monument moving for the application so must include an agenda item at the next meeting.

 SG to follow up the progress of the plans with Bernard. He is also investigating some historic monument moving specialists to give us professional advice on moving them.

SG is also contacting the Water, Gas and Electricity suppliers about the hall demolition.

Item 6 Church Centre update

We have received the first payment of £30,166 from the council. At the steering group meeting yesterday, there was discussion about the current timeline and it was felt it might be a bit optimistic. We have already begun to notify the users that the hall will be closing at the end of the year so we will probably continue to plan to close it to users in January 2013.

We will need to co-ordinate the clearing of the hall in early Jan – decisions will need to be reached on Traidcraft’s stock and activities, coffee in church etc.

We are proposing to site 2 temporary disabled toilets to the side of the SW door. These will only be in use for services.

Mike & Stephen have visited Upper Seagry hall and seen a modular build first hand. It is very well equipped and has given us some ideas on facilities which we will need to consider – audio/visual, screens, heat pumps.

Item 6 Property Checks – as part of our responsibility as a landlord, we need to periodically assess our properties for potential damage or hazards. Now that Upham Road has been sold, this leaves only 31 and 32 Cricklade Street.

Action: SG to discuss with Ailsa and the tenants appropriate times for the inspections. Also we should devise a checklist of items to check which would give more structure to the process as well as act as a record of each check. SG to investigate. We will need to do some more inspections – Mark and Daniel will join up to assess 32. Mike & Reg 31.


Item 7 31 Cricklade Street –
Dave Hobbs was awarded the contract and has nearly finished the work.

The old shed is in danger of falling down – SG to get a quote for a new one.

 

 Item 8. 58 Upham Road – has been sold.

 Any other business

 We have commissioned an asbestos surveys for St Mary’s, the church and the hall prior to commencing works.

 Billiard Table in Hall.  We have so far failed to find a home for the billiard table so will advertise it for sale.

 We will have to have the fire extinguishers checked

Query on PAT testing – how often does it really need to be done?

 

Next meeting date 14th November 2012 – 7.30 St Mary’s Hall

 

Deferred Jobs list

 

Job

Quote

Date

Rated A/B/C/D

SW door repair and draft exclusion

Defer to D&R

20/01/2010

C

Pressure washing the vestry steps

 

 

C

Flooding under the clergy vestry

 

25/03/2010

C

Cycle Racks

Defer to new hall

27/07/2010

C

Wall mounted Notice board at West door

£95+VAT

31/03/2011

C/D

Free standing Noticeboard at West door

£375+VAT S&I

31/03/2011

C/D

Sign for Church Centre (maybe directional signage rather than the name)

Defer

31/03/2011

D

New fireproof ceiling in the undercroft

 

20/02/2012

B/C

New central heating boiler & rads  31 CS

Est. 6k Oct 2011 DH

17/10/2011

C

 

A- Assessed as high risk

B- Legal requirement

C- Best Practice.

D – Nice to do.